FEATURED PROJECT
Eskom Pinotage Substation
Client
Eskom Holdings Limited
Location
Somerset West
Cost
R142m
Date Completed
January 2017
The expansion of Eskom’s 400kV yard and the building of a new 132kV HV yard. The Substation required the construction of a 58,000 m2 platform, 7,000 m3 of concrete works; 170 tons of structural steel, 1,200 m 2,4m high barrier security fencing and a 1,360m copper earth mat. The project was completed in January 2017.